Project description: |
Our Office was responsible for developing the hydraulic studies, which involved:
- Drainage – draining the main artery
- Hydraulic works along the main artery and drainage-drainage works on the internal of the tunnel
|
|
|
Completed works: |
- Preliminary study of hydraulic works
|
|
|
Works description: |
- 6.67km drainage – draining of the main artery (on the open sections)
- Culverts along the main artery
- 2.9Km sewerage and draining works on the Interior of the tunnel
|
|
|
Construction Cost: |
3.100.000,00€ |
|