Improvement of small harbour at Keri, Perfecture of Zante
| Country / Area : |
Greece / Keri - Zante Island |
|
| Institution : |
Perfecture of Zante |
|
| Duration of Service : |
2004 – 2012 |
|
|
|
More Information
|
|
| Project description: |
Design of reconstruction harbour works in order to improve the existing small port at Keri. The design purpose is the possibility of safe mooring in a fully functional harbour for 125 fishering and small cruise crafts. At the same time we have to consider the necessary environmental management infrastructure for preventing and responding to potential marine pollution in the environmentally sensitive area of the gulf of Laganas at west coast of Zante. |
|
|
| Completed works: |
- Preliminary study of harbour works
- Environmental impact assessment
- Coastal study with mathematical modelling
- Final study of harbour works (in preparation)
- Tender documents (in preparation)
|
|
|
| Works description: |
- 243.95m, windward quay wall with composite cross section and opening for water renewal
- 55.0m leeward mole with rubble mound of rock armour units
- 194.20m berth at the windward quay wall
- 141.0m berth at the seaside with mass concrete units
- 2 floating pontoons 70.0m each
- Slipway with concrete units
- Construction of necessary equipment for safety berthing at berths and floating pontoons
- Water and electricity supply networks
- 70 m2 aauxiliary and control building
- Compact system of wastewater treatment effluent
|
|
|
| Construction Cost: |
3,900,000.00€ |
|